Expand model tag support: add GLM-5.1, simplify Anthropic IDs, scan tags anywhere in message
- Flink update_bars debouncing - update_bars subscription idempotency bugfix - Price decimal correction bugfix of previous commit - Add GLM-5.1 model tag alongside renamed GLM-5 - Use short Anthropic model IDs (sonnet/haiku/opus) instead of full version strings - Allow @tags anywhere in message content, not just at start - Return hasOtherContent flag instead of trimmed rest string - Only trigger greeting stream when tag has no other content - Update workspace knowledge base references to platform/workspace and platform/shapes - Hierarchical knowledge base catalog - 151 Trading Strategies knowledge base articles - Shapes knowledge base article - MutateShapes tool instead of workspace patch
This commit is contained in:
@@ -0,0 +1,61 @@
|
||||
---
|
||||
description: "Capture or hedge the gross margin of a gas-fired power plant by trading the spread between wholesale electricity prices and natural gas fuel costs, using electricity and gas futures in the ratio determined by the plant's heat rate."
|
||||
tags: [miscellaneous, energy, spread-trading, hedging, commodities]
|
||||
---
|
||||
|
||||
# Energy — Spark Spread
|
||||
|
||||
**Section**: 14.4 | **Asset Class**: Miscellaneous (Energy Commodities) | **Type**: Spread Trading / Hedging
|
||||
|
||||
## Overview
|
||||
The spark spread is the difference between the wholesale price of electricity and the price of natural gas required to produce it. It measures the gross margin of a gas-fired power plant (excluding all other costs: operation, maintenance, capital, etc.). A spark spread position is built by taking a short position in electricity futures and a long position in natural gas futures, in the ratio determined by the plant's heat rate.
|
||||
|
||||
## Construction / Mechanics
|
||||
|
||||
**Heat rate** (fuel efficiency of the power plant):
|
||||
```
|
||||
H = Q_F / Q_E (516)
|
||||
```
|
||||
- `Q_F` = amount of fuel (natural gas) used, measured in MMBtu
|
||||
- `Q_E` = electricity produced, measured in MWh
|
||||
- `H` measured in MMBtu/MWh
|
||||
- MMBtu = 1,000,000 Btu; Btu ≈ 1,055 Joules
|
||||
|
||||
**Spark spread** (in $/MWh):
|
||||
```
|
||||
S = P_E - H × P_F (517)
|
||||
```
|
||||
- `P_E` = price of electricity ($/MWh)
|
||||
- `P_F` = price of natural gas ($/MMBtu)
|
||||
|
||||
**Hedge ratio** for futures contracts:
|
||||
```
|
||||
h = H × F_E / F_F (518)
|
||||
```
|
||||
- `F_E = 736 MWh` (standard electricity futures contract size)
|
||||
- `F_F = 10,000 MMBtu` (standard natural gas futures contract size)
|
||||
|
||||
Since `h` is generally not a whole number, it is approximated as the ratio `h ≈ N_F / N_E` with the lowest possible whole-number denominator `N_E`. The hedge consists of buying `N_F` gas futures contracts for every `N_E` sold electricity futures contracts.
|
||||
|
||||
## Return Profile
|
||||
- **Electricity producer (natural hedge)**: short electricity futures + long gas futures locks in a fixed spark spread, hedging against a compression of the gross margin
|
||||
- **Speculator / spread trader**: profits if the spark spread widens (electricity prices rise relative to gas prices) on a long spread position, or if it narrows on a short spread position
|
||||
- The strategy has no directional energy price exposure — only exposure to the relative price of electricity vs. natural gas
|
||||
|
||||
## Key Parameters / Signals
|
||||
- **Heat rate `H`**: plant-specific efficiency; lower `H` = more efficient plant = higher spark spread for the same fuel cost
|
||||
- **Spark spread `S`**: core signal; compare to historical average or fair value based on plant operating costs
|
||||
- **Contract sizes `F_E`, `F_F`**: determine the achievable hedge ratio granularity
|
||||
- **Seasonal patterns**: electricity demand (and spark spread) exhibits strong seasonality driven by heating/cooling demand
|
||||
|
||||
## Variations
|
||||
- **Dark spread**: same concept for coal-fired power plants (replaces natural gas with coal prices)
|
||||
- **Quark spread**: same concept for nuclear power plants
|
||||
- **Clean spark spread**: adjusts for carbon emission costs (CO2 allowance prices) in addition to fuel costs
|
||||
|
||||
## Notes
|
||||
- The spark spread measures gross margin only; it does not account for fixed operating costs, maintenance, or capital expenditures
|
||||
- Basis risk exists between the price indexes referenced in futures contracts and the actual spot prices at the delivery location
|
||||
- Liquidity is concentrated in front-month contracts; longer-dated spark spread trades may have wide bid-ask spreads
|
||||
- Heat rates vary with plant load and ambient temperature; a single fixed `H` is an approximation
|
||||
- Regulatory risk: electricity markets are often heavily regulated; price caps and dispatch rules can affect realized spreads
|
||||